Case Study - Quotient Clinical Nottingham

Project Address

Quotient Clinical
Ruddington
Nottingham
NG11 6JS

Project Details

Main Contractor : Signature Building Services Ltd
Project Date : August 2015 – January 2016

Project Overview

Signature Build were principle contractors for the job which involved the demolition of existing office space, and installation of 630m2 of new laboratories for a state of the art research and development facility. The job was completed on time and on budget to an excellent standard. The works were done with minimal disturbance to the staff working on the 1st floor, and the client was extremely impressed with our performance throughout the contract

Works Completed

• Managed the whole job, all trades and sub-contractors as principle contractor from start to completion
• New stud partitions
• Suspended ceilings
• Overboard existing raised access floor
• New Vinyl flooring installed throughout
• Installed new hygiene laminated doors
• All joinery/carpentry works
• Plastering
• Decorating
• Builders work in connection to mains power upgrade

• Builders work in connection to complete new M & E system
• Foundations for new plant room and solvent store
• Foundations for new generator base, and A/C units
• New steel frame plant room and solvent store
• Cladding to plant room & solvent store
• New foul drain system
• Fencing
• Paving
• Landscaping